Tuesday, July 9, 2013

INS Vikrant to be launched soon - first phase complete

After much delay, the Indigenous Aircraft Carrier (IAC), being built in Cochin, is ready for its launch on August 12. At the same time, the second carrier, INS Vikramaditya, will be undergoing extensive final sea trials in Russia.

While Vikramaditya should join the navy in early 2014, the INS Vikrant would take another three years. The 40,000-tonne aircraft carrier will cross a major development milestone when the ship would be launched by defence minister A.K. Antony, marking the end of the first phase of construction. 


INS Vikrant at Cochin Shipyard ( Image Courtesy - thehindu.com ) 

The launch would mean that the ship would be out of dry dock after completion of work related to fitting all underwater equipment like engines, gear box, shafting and diesel alternators. The construction of the complex warship was undertaken in two phases. Sources in the shipyard said some of the work from phase-II has already started and it is estimated that in two years the ship would be 90 per cent complete.

Despite the delays, the construction of an indigenous carrier is a major boost to country's ship-building capabilities. At the moment, 46 of 47 new naval warships are being built in domestic shipyards. Stealth frigate INS Trikand, which was commissioned in Russia, was the last ship ordered from abroad. Now only the delivery of INS Vikramaditya is awaited.

News Courtesy - indiatoday.intoday.in

Saturday, January 26, 2013

Indian Navy: Progress Report - INS Vikrant Aircraft Carrier

Over a year after its initial launch, the maiden indigenous aircraft carrier of the Indian Navy will be re-docked at Cochin Shipyard by the end of January 2013, for resumption of work.

Once back at the building bay for completion of work in the first phase, the carrier — currently weighing about 17,500 tonnes — will have its propulsion, shafting, generation and other engineering equipment fitted over the next five to six months before it gets floated out again.

Quite a bit of structural work, probably up to the flight deck, which would give the vessel some shape, will also happen during this phase of construction.


INS Vikrant II under construction at Kochi ( Image Courtesy - thehindu.com )

The project had hit a mechanical roadblock when reduction gearboxes made by the Gujarat-based Elecon Engineering Company Limited fell short of requirements. “Further construction of the carrier wasn’t possible without the huge gearboxes going in. The systems have now passed muster,” said a Navy source.

As the first IAC, to be named INS Vikrant on completion, undergoes birth pangs at the Cochin Shipyard, a second carrier, presumably a bigger one weighing almost 60,000 tonnes, is on the drawing board at the Directorate of Naval Design in New Delhi.

News Courtesy - thehindu.com

Wednesday, November 21, 2012

Airrcat Carrier INS Vikrant - Construction Progress Update

The Defence Ministry will soon move the Union Cabinet for an additional Rs. 2000 crore to meet the cost overrun for completing the first phase of Indigenous Aircraft Carrier (IAC) being constructed at the Cochin Shipyard - on India's western seaboard.

The IAC, which is likely to be named INS Vikrant, is likely to be over 40,000 tonnes and is biggest ship that India has ever built. The construction of the ship has been delayed due several reasons primarily because India was unable to procure special steel from Russia and also because gear boxes produced by a Gujarat-based firm in collaboration with the German partner had been found to be faulty.

Public sector giant, Steel Authority of India (SAIL) has come to rescue of the Indian Navy by producing the special quality steel. The first of the two remade gear boxes have reached Kochi a few days ago.


INS Vikrant under construction, at Cochin ( Image Courtesy - freewebs.com )

Defence Minister, Mr A K Antony who reviewed the progress of the construction of the ship today directed Defence Secretary Shashikant Sharma to constantly monitor the progress of the construction and formed empowered apex committee. Defence Minister Antony has asked Cochin ship yard to come with a "firm date of delivery". Sources said that Mr Antony has also told the shipyard that "we cannot go on hearing excuses. Everybody has to be accountable for the warship which is a national project and responsibilities in case of further slippages will have to be fixed."

The aircraft carrier is critical to India's ambition to emerge as a dominant player in the Indian Ocean region. Although India needs at least two, if not three, aircraft carriers, however, to ensure that it has at least one carrier available at all times, at present it is still pushing the 50 year old British made war horse INS Viraat.

With the USA likely to reduce its presence in the Persian Gulf, the Indian Navy desperately needs major assets like Aircraft Carriers to maintain its presence and also shape the developments in the volatile gulf region. "It is because we're uncertain about when we are likely to get the next carrier we have been keeping INS Viraat in the best shape possible," a senior Naval officer told NDTV. 

INS Viraat which has gone through over a dozen major and minor refits, is currently undergoing another refit is likely to be in the docks and out of action till March 2013. This refit will make the carrier operational, at least till 2020.

News Courtesy - ndtv.com